Hi,
I looked in to conservatories and I think I'd prefer to put some extra effort in and get a proper extension.
Firstly, I'd like to plan this myself if it means I save thousands, if I'm unlikely to save anything and better off going to a one stop shop then let me know.
I want to be sure of the steps that are required and which tradesmen I would need at which point.
My list as follows:
Architect - plans
Building control application
Welsh water build over agreement (build over sewer pipe with lintel)
Dig foundations - general labourer?
Concrete poured for footings - who to get?
Bricklayer in to lintel over the sewer pipe?
Welsh water and building control called out to inspect lintel
Bricklayer to finish the shell including moving my existing window and door and adding another window.
Concrete floor? I have no idea
Roof - roofer
Electrician first fix
Plasterer to board and skim internals.
Electrician 2nd fix
2 radiators - plumber
Carpet laid.
Doorframes and skirting - diy
Painting and decorating - diy
I'm a little confused at who would be responsible to insulate, Plasterer or Bricklayer?
I'd like to at least get the stages in my head, in the correct order and who to contract for each job.
Any advice greatly welcomed
Ian
I looked in to conservatories and I think I'd prefer to put some extra effort in and get a proper extension.
Firstly, I'd like to plan this myself if it means I save thousands, if I'm unlikely to save anything and better off going to a one stop shop then let me know.
I want to be sure of the steps that are required and which tradesmen I would need at which point.
My list as follows:
Architect - plans
Building control application
Welsh water build over agreement (build over sewer pipe with lintel)
Dig foundations - general labourer?
Concrete poured for footings - who to get?
Bricklayer in to lintel over the sewer pipe?
Welsh water and building control called out to inspect lintel
Bricklayer to finish the shell including moving my existing window and door and adding another window.
Concrete floor? I have no idea
Roof - roofer
Electrician first fix
Plasterer to board and skim internals.
Electrician 2nd fix
2 radiators - plumber
Carpet laid.
Doorframes and skirting - diy
Painting and decorating - diy
I'm a little confused at who would be responsible to insulate, Plasterer or Bricklayer?
I'd like to at least get the stages in my head, in the correct order and who to contract for each job.
Any advice greatly welcomed
Ian