We are into the final push on the villa as its only just over a week till the removal guys turn up. In this time we still need to install the shower screens, paint the ceiling and plumb in sinks and taps in the bathrooms and finish off the kitchen.
The Corian turned up today and work will start on the countertops early next week (pic below is of 7 sheets of 3m length Designer white corian)
New ceiling in the master bathroom was being prepped for down lighters
The guest bathrooms have had the toilet installed and shower column installed. Work was moving ahead on the vanity units:
As for the annexe this is cracking on at a great pace with the ceiling going on today:
So one big push over the next week and I really think it will be done but it will need a good clean before we move in.
The Corian turned up today and work will start on the countertops early next week (pic below is of 7 sheets of 3m length Designer white corian)
New ceiling in the master bathroom was being prepped for down lighters
The guest bathrooms have had the toilet installed and shower column installed. Work was moving ahead on the vanity units:
As for the annexe this is cracking on at a great pace with the ceiling going on today:
So one big push over the next week and I really think it will be done but it will need a good clean before we move in.