I posted about this in the 'Windows and Other Software' sub-forum a while back, but only got one answer which unfortunately didn't help.
Basically I need to produce a Gantt chart for a project that will run 7 days a week for 8.5 worked hours a day.
I've tried all kinds of things but I just can't get it to do what I want. Is there a simple and well defined method I can use to get this damn software to play ball, because it's driving me mental?
I just need something that works!
I've set all my activities for the project and given them their durations, but I'm utterly stuck at changing to a 7 day working week. Help!!
Basically I need to produce a Gantt chart for a project that will run 7 days a week for 8.5 worked hours a day.
I've tried all kinds of things but I just can't get it to do what I want. Is there a simple and well defined method I can use to get this damn software to play ball, because it's driving me mental?
I just need something that works!
I've set all my activities for the project and given them their durations, but I'm utterly stuck at changing to a 7 day working week. Help!!