I thought we would see loads of new cases by now?
PC-Q12LA
Typically the products at Computex are pre-production samples.
Once showcased, manufacturers typically then have to start work on tooling for mass production, this can take 2-3 months, then the first production runs can take 4-6 weeks, and then shipping from Asia to Europe can take another 3-4 weeks too.
So effectively that is up to 5-6 months.
P.S. Tooling costs can run in to hundreds of thousands of dollars to get sorted too.
Is that Air 240 taking ATX or just micro/mini?