MS Project 1 Day != 1 Day

Soldato
Joined
20 Feb 2004
Posts
23,394
Location
Hondon de las Nieves, Spain
I've been trying to play around with MS Project recently and had some issues.

I've set up my calendar so that i'm on 7 days per week with 12 hour days 08:00 to 20:00

P61dX01.png


I've also made sure my hours per day is correct

Ks0RutT.png


Yet when i enter 1 day as the duration in the Gantt chart, it wants to span 2 days. To me if i start a task on the 23/01/17 and it takes 1 day it should finish on that 1 day but it's not playing ball. Same thing happens on other days. So Task 2 is for 2 days but shows as 3 days to complete.

Vpho9yi.png


Anyone have any ideas? I've also found that when looking at the Resource Chart it shows task 1 as 1.33 days. This suggests that there is still something using an 8hr day as 12hrs would be the equivalent to 1.33 days.

Wf2BE8i.png
 
Last edited:
Ignore, i was a colossal fool and just realised that even though i'd set up the new calendars my actual project wasn't set up to use the new calendar :o
 