Pricing a refurbishment of a 187 sq m bungalow. Spec calls for over boarding all the ceilings and removing and replacing the loft isolation plus a full rewire and plumb.
Do you think there will be any cost difference between pulling all the ceilings down and renewing or just over boarding?
Positives
Less time for plumbers and sparky as all the m&e is loft down.
Stripping out of ceilings will bring insulation down as well Saving time pulling insulation up in loft.
Original ceiling may be uneven anyway
Negatives
Additional skips
Additional time
Anything else?
Pricing a refurbishment of a 187 sq m bungalow. Spec calls for over boarding all the ceilings and removing and replacing the loft isolation plus a full rewire and plumb.
Do you think there will be any cost difference between pulling all the ceilings down and renewing or just over boarding?
Positives
Less time for plumbers and sparky as all the m&e is loft down.
Stripping out of ceilings will bring insulation down as well Saving time pulling insulation up in loft.
Original ceiling may be uneven anyway
Negatives
Additional skips
Additional time
Anything else?