Spain House Build - Building Started

So, after being told around the time of the above post that the builder expects the house walls to be up by "mid September", i went by yesterday and nothing has happened again. He's again blaming the 3rd party builders, and saying he needs to find some new builders to take over. I let my frustration take over, and told him i had been considering cancelling the contract since July and had been beyond patient up until this point but enough is enough and given the current situation i have no confidence he can deliver and how it could easily be another 2 months before he finds someone else to start the project.
It would help his case a little bit if he had at least delivered on the non build related queries, but it's radio silence on those too.

I got in touch with another builder i briefly spoke with back in July on the phone. Have sent him the documentation for the build, so will see what he says.
 
Cheers. I'm open to conversations with the existing builder but i think i'd want to amend the contract to include multiple financial penalties and compensation. I mentioned something similar earlier in the thread but never had the conversation with him as we started to see a little progress. However we've now really lost belief and i think it's better to cut ties whilst it's at the current stage than have any small progress.

The main concerns are around financing a new builder. Whilst we've not paid the existing builder a huge amount, there's probably an element we'd need to reclaim and who knows how tricky that could be. The bank will then only pay out at various stages and so we'd need to try and hope the new builder could self fund to hit the first bank payment. We have some cash, but not massive amounts
 
doesn't everything stop for the summer holiday in Spain ? if your developer is starting any new builds must have the same issue of finding builders;
couple of medium builders I know in uk have a team of people 15-20 and are doing multiple builds/renovations in parallel for the economy of scale,
and you can see what tasks are ongoing by their prominent builders signage, but it sounds like builders in spain maybe much smaller concerns ?
 
Sorry to hear this too :(

You are very much braver than me! I'd certainly want to bin him off and start by employing a builder to just get the waterproof plastered shell with basic electrics/plumbing in.. (i.e. drains, hot/cold mains, central heating pipework if needed, etc)..
Then I'd look at other contractors for flooring/kitchens/bathrooms etc..
 
doesn't everything stop for the summer holiday in Spain ? if your developer is starting any new builds must have the same issue of finding builders;
couple of medium builders I know in uk have a team of people 15-20 and are doing multiple builds/renovations in parallel for the economy of scale,
and you can see what tasks are ongoing by their prominent builders signage, but it sounds like builders in spain maybe much smaller concerns ?

Some does, but generally only ~ 2 weeks. There is a new build near out rental which has had had builders out all over August.

Sorry to hear this too :(

You are very much braver than me! I'd certainly want to bin him off and start by employing a builder to just get the waterproof plastered shell with basic electrics/plumbing in.. (i.e. drains, hot/cold mains, central heating pipework if needed, etc)..
Then I'd look at other contractors for flooring/kitchens/bathrooms etc..

I think it's the whole "better the devil you know thing". Spain is rife with horror stories of builders ripping people off and this was the only guy who actually came with a great reputation. The issue organising it ourselves is when/if things go wrong everyone blames each other and with the language barrier and cultura differences i'd much rather have a single point of contract for any problems.

Amusingly the other builder i'd been in touch with and who said he'd be in touch in 2-3 days has now been silent for ~9 days!


Small update generally. I've been off work since the 10th. In the meantime i've had some further conversations with our current builder. He subcontracts to 2 separate teams depending on the build type. Ytong blocks go to one team and anything with double skinned thermoclay bricks and insulation go to another team. Seems it's the bricklayer team with the Ytong blocks which is the issue and just not doing what they're being paid for. Presumably because they have jobs they're employed directly for which are being prioritised. He's asked if we'd switch to the double skinner thermoclay build type with some compensation for the disruption. Then an agreed penalty for anything beyond March fined at €100/day. He's assured us that the other building team will put our build as a priority and has now confirmed he's having to remove the original team from his subcontractors and find someone else who can work with Ytong or just stop offering it as an option (i'm still not sure why different builders can't use different bricks!)

I've had a discussion with the architect who's confirmed the energy/sound insulation rating would be equal between the two (and sound probably better with the clay brick due to multiple layers/thickness). I'm waiting for details about how the foundation would be impacted as the wall thickness would be thicker and so the current base isn't wide enough. The only downside at the moment seems to be the overall size of the build, but given our plot size, this wouldn't cause any issues.

The saga continues!
 
Ytong blocks go to one team and anything with double skinned thermoclay bricks and insulation go to another team
both types have a similar external aesthetic then ? - I'd thought earlier pictures you'd shown with a light stone appearance was exclusive to ytong,
... and any cost differential between the two types dwarfed by labour cost I guess.
 
both types have a similar external aesthetic then ? - I'd thought earlier pictures you'd shown with a light stone appearance was exclusive to ytong,
... and any cost differential between the two types dwarfed by labour cost I guess.

Yeah. Both options get rendered so appearance is irrelevant.

As you say I think red brick may end up slightly more due to labour. Ytong is €6/brick and clay is probably around €1.70 each. Double that and add insulation and extra labour and it’s probably similar.

Been trying to find much comparisons between the two types to be confident I’m not being railroaded but struggling. Think I was sold on Ytong initially as it seemed “new and premium” but beyond the reduced labour and space saving I can’t see much arguments for it.
 
Back
Top Bottom