I can't because it is a different company. It may have the same sponsor, but it is completely different. Whislt we are sharing some of our lessons learned I don't have much exposure to CRL2 any more than you or anyone else!
However, on average it costs something like £150k per meter for a tunnel. So you have considerably more tunnelling. Also, from the map, it looks like it interfaces with a lot more NR lines than CRL does, so adds a huge amount of complexity to interfaces, connections and signalling. The line uses existing infrastructure, the new lines are only the tunnels through London. So there is a lot more complexity with CRL 2 owing to the fact there are more spurs to other lines run by other operators and NR.
This is just a guess as I don't work for them.