I have had to make a few trips out of the country but luckily my good mate and Father have been around to work with the contractor and keep things moving along.
There has been a lot of work done on the AC ducting and kitchen exhaust route in the ceiling of the kitchen and there is just about ready to receive the cooker hood:
In the study the new ceiling has been installed (ripped out when the en-suite was removed), new AC ducting and exhaust and the down lighters are ready to go in:
The dead space under the stairs will now have a cupboard - mainly for storing suitcases and the like:
Work is ongoing on the master bathroom - plumbing has been done so the tiling is happening now. This wall will have the mirror, vanity units and some cupboards:
The shower wall will feature floor to ceiling mosaic tiles along with two over head drenchers. Just above the tile line they will make some recesses for shampoo bottles etc
The rest of the walls in the master bathroom will have the large tiles contrasting against the mosaic for the shower wall:
Another team of guys are busy spraying the various doors:
and they seem to have done a decent job on all the drawers:
Outside of this plenty of other work going on as the final electrical points are put in place for the kitchen, a water line installed for the fridge, the architraves are being sprayed and we finalise the kitchen design.
This week should also see the installation of the Nest smoke alarms and the Ubiquity Access Points.
It is just over 4 weeks till the removal men deliver our furniture so the pressure is on the contractor!