This may end up as a bit of a project thread but as we are still pre-exchange it may fizzle out. There are no chains in either direction and no mortgage.
The bungalow in question is a typical three bed, built in 1987 and is need of quite a bit of updating.
Tasks identified from the Homebuyers survey are:
Rewire,
New CH boiler and CH checks, possibly rads;
New kitchen, old one falling to bits.
Obviously the decor needs smartening and new floor coverings throughout. Walls floors and roof are good.
We have decided to knock through kitchen and dining room and fill the arch between dining and living room to give two decent sized seperate rooms.
This is giving us some sleepless nights already as the timescale for the major items is short. Possible exchange / complete in early November, we are in rented with two months notice to give so that gives a bit of leeway but we would like to complete the wiring, plumbing removal of wall, kitchen and carpeting before we move in.
Christmas and general time of year possibly makes a big hole in getting trades in?
I have proposed diverting gas supply to repositioned hob and gas fire in the lounge via the roof space first, then removing the wall. Next a complete rewire and replace the boiler. Lastly build the new kitchen and lay carpeting throughout the house.
Any thoughts on this being complete to move by end of January? I thought possibly end of February.
All comments are welcomed, on timescales, winter working, anything else.
The bungalow in question is a typical three bed, built in 1987 and is need of quite a bit of updating.
Tasks identified from the Homebuyers survey are:
Rewire,
New CH boiler and CH checks, possibly rads;
New kitchen, old one falling to bits.
Obviously the decor needs smartening and new floor coverings throughout. Walls floors and roof are good.
We have decided to knock through kitchen and dining room and fill the arch between dining and living room to give two decent sized seperate rooms.
This is giving us some sleepless nights already as the timescale for the major items is short. Possible exchange / complete in early November, we are in rented with two months notice to give so that gives a bit of leeway but we would like to complete the wiring, plumbing removal of wall, kitchen and carpeting before we move in.
Christmas and general time of year possibly makes a big hole in getting trades in?
I have proposed diverting gas supply to repositioned hob and gas fire in the lounge via the roof space first, then removing the wall. Next a complete rewire and replace the boiler. Lastly build the new kitchen and lay carpeting throughout the house.
Any thoughts on this being complete to move by end of January? I thought possibly end of February.
All comments are welcomed, on timescales, winter working, anything else.