May I ask why did it take 4 days? How many hours per day and how many people?
What exactly was done?
Ours took 4 days (was meant to be 5 but got condensed to 4 due to an issue with scaffolding not turning up - they didn’t want to start if they couldn’t finish).
There were up to 5 people on site at a time, 3 plumbers and 2 electricians. 2 of the plumbers were relatively inexperienced and one was experienced.
The electricians were there part of the time, the plumbers are there full time, one day they were there until 7pm due to the condensed timetable.
I didn’t have an existing cylinder or a pressure relief overflow as my system was vented. Other than the cold supply, hot out, flow and return locations being already in place, they had a bit of a blank canvas.
Essentially the jobs for the plumbers were:
Decommissioning existing boiler and removing it and any existing cylinder.
Swapping X radiators for larger ones (8 in my case).
Running new 28mm flow and return from the heat pump up the side of the house, through the loft and down into the airing cupboard - in my case it’s a good 15m each for the flow and return.
Install a new pressure relief and D20 pump for pressure relief over slow (through the loft and out the side of the house).
Install new cylinder, expansion vessel, 3port valve and associated pipework.
Install a volumiser on the heating return
Install a magnetic filter after the heating and hot water returns merge.
Build a gravel soak away and base for the heat pump.
Install the heat pump itself on to anti vibration blocks(at least a 2 man lift to do it safely - 88kg).
Commission heat pump
Balance the radiators
Electricians had to:
Install a new power supply for the heat pump.
Install new supply for the immersion
Install wiring for the controls back to the heat pump
Install in the controls themselves
Install the external temperature sensor
Install the wired thermostat.
It’s A LOT of work.
Edit: at some point in the install someone from the local gas network turned up and capped the gas and removed the meter.