Small update.
So things are moving again.
I have been out of the uk for the last 6 to 10 months so not much has happened.
I have decided to project manage the rest of the build my self, so I have employed a couple of builders and I am on site everyday with them.
We have plastered all the walls in gyproc soundcoat its a parge coat for increased airtightness to optimize sound and thermal performance.
http://www.british-gypsum.com/produ...gyproc_accessories/gyproc_soundcoat_plus.aspx
we got through 75, 25kg bags of the stuff in total.
We installed a new smoke vent velux window at the top of the stairs.
It allows some light in but also it will vent smoke in the even of a fire.
We have finished the first fix electrical work now, we have around 250 light fitting and 100 twin sockets.
Unfortunately I was stupid enough to give the electrician a £3k deposit when he decided to keep after doing just 3.5 days work. I found someone else now and I am taking the old one to court.
As you can see we got through a lot of cable
I have installed 15 and 22mm hot and cold water supplies from the manifolds to the sinks, baths, WC’s…..
This is a photo of bathroom 2 manifold, it also supplies the kitchen and utility room.
manifold in bedroom 4 with the UFH manifold next to it.
we have had to pull up a lot of the floors to get the cables and pipes in
so we have spent the last 4 days putting the OSB floors back down
The dorma windows are finally finished.
We have had such a nightmare with them, we paid £9k for top end aluminum windows but the idiots manufactured them wrong and they ended up flooding the flat directly under us.
oh and we got our self a new pupply
the plan going forward:
Next week I am going to put all the waste pipes in, I need to vent some of them through the roof so I am going to have to put up scaffolding again
Then I am on holiday for a month to Thailand so nothing will happen until I get back. After the trip we plan to start plaster boarding the walls and ceilings, after that we are going to install the floor and under floor heating
Then the kitchen, bathrooms and decorating. I expect to be finished by March at the latest.
So things are moving again.
I have been out of the uk for the last 6 to 10 months so not much has happened.

I have decided to project manage the rest of the build my self, so I have employed a couple of builders and I am on site everyday with them.
We have plastered all the walls in gyproc soundcoat its a parge coat for increased airtightness to optimize sound and thermal performance.
http://www.british-gypsum.com/produ...gyproc_accessories/gyproc_soundcoat_plus.aspx
we got through 75, 25kg bags of the stuff in total.

We installed a new smoke vent velux window at the top of the stairs.

It allows some light in but also it will vent smoke in the even of a fire.
We have finished the first fix electrical work now, we have around 250 light fitting and 100 twin sockets.
Unfortunately I was stupid enough to give the electrician a £3k deposit when he decided to keep after doing just 3.5 days work. I found someone else now and I am taking the old one to court.
As you can see we got through a lot of cable



I have installed 15 and 22mm hot and cold water supplies from the manifolds to the sinks, baths, WC’s…..
This is a photo of bathroom 2 manifold, it also supplies the kitchen and utility room.

manifold in bedroom 4 with the UFH manifold next to it.

we have had to pull up a lot of the floors to get the cables and pipes in



so we have spent the last 4 days putting the OSB floors back down




The dorma windows are finally finished.


We have had such a nightmare with them, we paid £9k for top end aluminum windows but the idiots manufactured them wrong and they ended up flooding the flat directly under us.
oh and we got our self a new pupply

the plan going forward:
Next week I am going to put all the waste pipes in, I need to vent some of them through the roof so I am going to have to put up scaffolding again
Then I am on holiday for a month to Thailand so nothing will happen until I get back. After the trip we plan to start plaster boarding the walls and ceilings, after that we are going to install the floor and under floor heating

Then the kitchen, bathrooms and decorating. I expect to be finished by March at the latest.
Last edited: