The progress of the build hit a bit of a problem, basically the joiner and the builder fell out and the builder ended up sacking the joiner even though I was very happy with the work he had done, personalities do clash I suppose, but the joiner was basically not doing what the builder was telling him so there you go.
The good news is the room has now been plastered as the pictures show so the coffer will now be built by a different joiner next week.
So the sequence of events from now will be -
- Complete the build of the coffer.
- Install the ceiling grilles and complete air-con installation.
- Cut holes in the ceiling for the four ceiling speakers.
- Install the star fibre optic lighting in the ceiling.
- finish the electrics installation.
- Paint and decorate the room.
- Fit the carpet.
- Fit the AV kit.
- Get some seating.
I'm expecting an eye watering bill from the builder when he is finished so things may slow down a bit depending on finances.