I guess he's insinuating that Blue Square is not one of the highest quality data centers.

Nothing, BSQ is only 4 years old and is light years ahead of other DCs in terms of facilities and service. It's a full Tier III datacentre, above what many hosts use including some rather pricey hosts.I guessed that
Just wanted to know exactly what he meant. I.E what does Bluesquare lack that more modern data centers have?
Nothing, BSQ is only 4 years old and is light years ahead of other DCs in terms of facilities and service. It's a full Tier III datacentre, above what many hosts use including some rather pricey hosts.
Obviously something serious went wrong today however which will require a full review to decide what to do going forward. Power outages shouldn't happen.
They're checking the UPSs to do the switch back, but given what the UPSs have done today I'm comfortable with taking a large can of diesel to the DC every morning....Thanks Beansprout.
Do you know when we will be back on mains?
They're checking the UPSs to do the switch back, but given what the UPSs have done today I'm comfortable with taking a large can of diesel to the DC every morning....
(Note, that of course is a joke!)
Does anyone experience any of the below, or is it just me? Even if it is, UPSs only give you time to shutdown cleanly - stuff still has to be powered back up.I was under the impression that colo customers would have their own rack based UPSs in addition to the data centres, is this common practice?