Day 2 (half day):
Got my days wrong so ended up digging in the wet. Thank god it was easy going and clay is only 500mm down. 10 middle holes knocked out in a couple of hours.
The ballast and cement comes tomorrow. I think I will be a bit short but I am hoping to get the lot concreted, so I can start the base by Wednesday. I imagine base and joist hangers will take a full day (92 of the things...).
Annoyingly Tool Station is worse than their 3rd party suppliers. So the order I placed Saturday has been fulfilled for the bits they don't flog but not the main stuff I need (twist nails, splice plates etc...).
--------------
Day 3:
Start the clock:
10:39
Stop the clock:
17:04.
Dead.
Almost had a life changing incident with the mixer too. It actually became unbalanced and fell over. Thank god I got the kill switch before it took my arm off. Deadly things
------------------------
Day 4:
Slow day today. I barely slept - my carpal tunnel is kicking my ass. I need the operation on both hands but just don't fancy it enough
Lost a chunk of the day "hiding" some of my rubble before covering it with the weed membrane. Then lost an equal part of the day levelling off the nut/rod system. It is very satisfying to be fair.
Also had to put a billion twist nails in the splice plates to make some 6m lengths...
(I don't think you need all nails but I was waiting for help to arrive as it isn't a one man lift )
Got 3 in as the fourth requires the offcut of the 3.5m splicing into the 4.8m and I ran out of brain cells so called it at this point...
Myperfect engineering luck saw the rod system fall perfectly though. I don't even need to cut this, as it leaves just enough for a nut.
Tomorrow is going to be tough as my wife is at work and despite her being super pregnant she was critical to the lifting of the 6m+ lengths. I am hoping I can YOLO the last one and the sides are easy (3.5m each).
I can then chill out and spend the day doing joist hangers...
---------------------------------
Day 5 -
Super slow progress today. I had to single lift the 3.5m spans and then the 6m big boy. Everything is bolted down now. Then started to tackle the joist hangers which have become another one of my top-least-favourite-things-ever.
My hands are FUBAR so it is tough going now. The roof arrived as a bit of a tease tho
--------
Day 6:
Hand balled all the materials into the workshop today, will have to stop progress from tomorrow as I need to recover (my hands are FUBAR). Decent shift today but not as far ahead as I wanted unfortunately.
Joist hangers are a new least favourite job. 14 nails per joist hanger, x84
Got the PIR down... debating what to do now. I can put the 22mm down easily enough but the weather is going to turn next week. I don't own a tarp big enough!
----------------
Day 7 (half day):
Had a super slow casual day today. I guaranteed myself tomorrow "off" so I can be at least partially productive on Monday.
In a cruel twist of events I am short by about 1.5feet of 22mm (the build pack is off by 1 board for the floor [need 16 boards not 15]). Ironically I listed about 30 offcuts of 22mm from the living/dining/kitchen/hall job on Marketplace just 5 days ago and some lad took the lot away
^ having my 3/yo mark out joist centres may have been an error in judgement. She was doing a great job then got distracted and just started drawing lines everywhere lol.
All pause now until May 25th(ish).
----------------------------------------------------
Any recommendations on internal floor? I may go Desert Oak from Floor Street again. I also underestimated the cost of front cladding. And I also need soffits/fascias!
Thanks
Got my days wrong so ended up digging in the wet. Thank god it was easy going and clay is only 500mm down. 10 middle holes knocked out in a couple of hours.
The ballast and cement comes tomorrow. I think I will be a bit short but I am hoping to get the lot concreted, so I can start the base by Wednesday. I imagine base and joist hangers will take a full day (92 of the things...).
Annoyingly Tool Station is worse than their 3rd party suppliers. So the order I placed Saturday has been fulfilled for the bits they don't flog but not the main stuff I need (twist nails, splice plates etc...).
--------------
Day 3:
Start the clock:
10:39
Stop the clock:
17:04.
Dead.
Almost had a life changing incident with the mixer too. It actually became unbalanced and fell over. Thank god I got the kill switch before it took my arm off. Deadly things
------------------------
Day 4:
Slow day today. I barely slept - my carpal tunnel is kicking my ass. I need the operation on both hands but just don't fancy it enough
Lost a chunk of the day "hiding" some of my rubble before covering it with the weed membrane. Then lost an equal part of the day levelling off the nut/rod system. It is very satisfying to be fair.
Also had to put a billion twist nails in the splice plates to make some 6m lengths...
(I don't think you need all nails but I was waiting for help to arrive as it isn't a one man lift )
Got 3 in as the fourth requires the offcut of the 3.5m splicing into the 4.8m and I ran out of brain cells so called it at this point...
My
Tomorrow is going to be tough as my wife is at work and despite her being super pregnant she was critical to the lifting of the 6m+ lengths. I am hoping I can YOLO the last one and the sides are easy (3.5m each).
I can then chill out and spend the day doing joist hangers...
---------------------------------
Day 5 -
Super slow progress today. I had to single lift the 3.5m spans and then the 6m big boy. Everything is bolted down now. Then started to tackle the joist hangers which have become another one of my top-least-favourite-things-ever.
My hands are FUBAR so it is tough going now. The roof arrived as a bit of a tease tho
--------
Day 6:
Hand balled all the materials into the workshop today, will have to stop progress from tomorrow as I need to recover (my hands are FUBAR). Decent shift today but not as far ahead as I wanted unfortunately.
Joist hangers are a new least favourite job. 14 nails per joist hanger, x84
Got the PIR down... debating what to do now. I can put the 22mm down easily enough but the weather is going to turn next week. I don't own a tarp big enough!
----------------
Day 7 (half day):
Had a super slow casual day today. I guaranteed myself tomorrow "off" so I can be at least partially productive on Monday.
In a cruel twist of events I am short by about 1.5feet of 22mm (the build pack is off by 1 board for the floor [need 16 boards not 15]). Ironically I listed about 30 offcuts of 22mm from the living/dining/kitchen/hall job on Marketplace just 5 days ago and some lad took the lot away
^ having my 3/yo mark out joist centres may have been an error in judgement. She was doing a great job then got distracted and just started drawing lines everywhere lol.
All pause now until May 25th(ish).
----------------------------------------------------
Any recommendations on internal floor? I may go Desert Oak from Floor Street again. I also underestimated the cost of front cladding. And I also need soffits/fascias!
Thanks