I self installed 25 panels and 20kw storage. Wired up and new circuits done by electrician.
I have just paid Octopus for the non MCs export. I have saved a fortune by going this route.
So far the system has cost me circa 13.5k. But for that I have:
10.5kw panels
6kw hybrid inverter
20kw storage in heated cab
New consumer unit for the circuits
All certs apart from MCs.
I think once you have an MPAN it matters not what happens with Octopus moving forwards.
I have just paid Octopus for the non MCs export. I have saved a fortune by going this route.
So far the system has cost me circa 13.5k. But for that I have:
10.5kw panels
6kw hybrid inverter
20kw storage in heated cab
New consumer unit for the circuits
All certs apart from MCs.
I think once you have an MPAN it matters not what happens with Octopus moving forwards.