Victorian renovation build log

E160B90F-2DD6-4A6F-8D93-DE834A9CB472_zpscbyr76sf.jpg
 
stripped and refinished the pew




used screwfix own brand stripper with wire wool and elbow grease

finished with beeswax/turps pre-mixed
 
patio still not done, unreliable builders if they didn't do such a good job on the kitchen would have looked elsewhere by now!

however the whole house is being scaffolded tomorrow for a re-roof and attic conversion extension.



this is the plan.

There is already a room in the attic so stair case is there, but it was only the servants quarters so single plug socket, no heating and only window looks into the alley between my neighbours.

Every bedroom in the floor below has a different celing height so opening up the whole attic means I've had to be inventive with floor levels!

I hope that all makes sense!
 
2 days into the strip out and the dust is unbelievable, the walls a ceiling have been removed.



nice surprise is the section of the attic I couldn't access is much bigger than expected so the bathroom with probably grow to include a roll top bath



also bigger than expected is the day-bed area, no quite sure what to do with it to be honest

 
It's going well except they still waiting for the roofers to start stripping the slate off.

Plan is to salvage as much of the old slate as possible and use salvaged Welsh slate where needed. All with membrane underneath and copper nails. Also having the bay window bitumen roof replaced with lead sheet.

I've asked for 150mm kingspan or equivalent to be fitted under the joists, but the builders are keen to go with 100mm......
not convinced
 
joists are only 75mm so after leaving 50mm for ventilation could only put 25mm in.
This means it will have to be battened out regardless
 
indeed, you need roughly 300mm rockwool for the equivalent 150mm PIR insulation. Where I have a large roof void i have used 300mm rockwool. Rockwool has better sound deadening properties so will be used in the floors and internal walls

u-value with 150mm = 0.18 W/m²K

u value with 100m = 0.31 W/m²K
 
finally they have started on the roof...... just as its forecast thunder storms! :lol:
came home to this

IMG1317.jpg


IMG1319.jpg


IMG1318.jpg


oh and have insisted on 150mm PIR insulation
 
all the roofing felt nearly on, they are starting to cut the velux frames in.

I've had a last minute change of mind and increased the size of one of the velux - much bigger

This will mean move both stud wall back to where the large purlins are (where they should have been to start with in my opinion)

windows are from roofingsuperstore and they were great with the exchange/return
 
Thats an awesome looking house, have never seen a semi like that have a garage built in.

thanks! For some reason the whole area is semis regardless of size, ours is one of the smaller ones!

the garage is the old basement dug out, done by the previous owners, needs a bit of work and the door is quite narrow but much better use of space.
 
unfortunately they paved it with horrible concrete slabs, plan is to replace with granite sets and have a proper drain channel fitted at the bottom of the garage door..... but other priorities for time being

IMG1322.jpg

bedroom window framed

IMG1321.jpg

bathroom window framed - you can see the stud wall will have to be moved back

IMG1323.jpg

size of the bedroom window and the replacement I ordered
 
well this has lost all momentum, no roofers for over a week, water leaking into every room, ceilings and original cornice starting to crumble and me and my 5 month pregnant wife intermittently sleeping on the sofa

:(
 
Roof finally on and weather tight!

scaffolded for 4 weeks for 7 days work (and not even full days)

Water damage to all the bedrooms in the meantime

And to cap it all off the suntunnel is about a metre from where it should be so will now go through the middle of the bedroom to the hall!

Useless, needless to say they aren't getting their final installment!
 
little update:

head builder cam round and sorted everything without me even asking, faith restored!

Its always an emotional roller-coaster getting big building work done :p


so while the scaffold was up decided to pack my chimney with Micafil insulation (between the old chimney and the liner)
this stuff...
IMG1354.jpg


made a spout in between the liner and stack and poured 100 litres of it in!

IMG1355.jpg


It started coming out in the living room so clearly the register plate was never sealed, explains the drafty front room :rolleyes:
(fire cement on order to fix this)
 
Back
Top Bottom